Les Excavations Payette / Description

PROJECT
National Bank Headquarters (800 Saint-Jacques St.)

Excavation work for the construction of National Bank’s new head office at 800 Saint-Jacques Street in Montreal. The deep excavation mandate was carried out at the same time as the excavation of the Victoria sue le Parc project at 700 Saint-Jacques Street.

Les Excavations Payette / Special Challenges

01

Special Challenges

  • Two separate projects completed in one excavation
  • Excavation at a depth of more than 20 m
  • Over 250,000 m³ of soil and rock excavated and transported
Les Excavations Payette / Video

02

Project video

Les Excavations Payette / Pictures

03

Pictures

04

Other project